Editing purchase requisitions and orders with cost allocation adjustments
As a shopper, you can modify purchase requisitions (PRs) and purchase orders (POs) while maintaining cost allocation across multiple cost centers.
Example use case for editing a purchase with multiple cost centers
In this example, a shopper creates a PR with cost allocation distributed between two cost centers, Customer Success and Engineering. The costs are assigned based on predefined percentages.
Suppose 20% is allocated to Customer Success and 80% to Engineering.
Cost allocation across multiple cost centers
If you purchase 6 quantities of the energy monitoring device priced at $230 each. The total cost amounts to $1380.
Purchase products in Shopping Hub
The cost for this purchase is allocated as follows:
- Customer Success Cost Center: $276 (20% of $1380)
- Engineering Cost Center: $1104 (80% of $1380)
Initial amount with cost allocation adjustments
Now suppose you edit the PR or PO to increase the quantity from 6 to 10 pencils. The total cost amounts to $2300.
Increase purchase quantity by editing a purchase.
In this case, the total cost is proportionally distributed between both the cost centers based on the original allocation:
- Customer Success Cost Center: $460 (20% of $2300)
- Engineering Cost Center: $1840 (80% of $2300)
Final amount with cost allocation adjustments
The cost allocation remains consistent when modifying purchase quantities in a PR or PO.
For more information, see Cost allocations.
Parent Topic:Purchase revision flows
Related topics
Edit a purchase line from a purchase requisition or order
Edit a purchase line from a purchase requisition or order from Employee Center (EC)