Create a test execution suite in Test Management 2.0
Create a short test plan when the testing effort is minimal and you do not want to go through the overhead of creating a test plan and a test cycle for a test execution suite.
Before you begin
Role required: sn_test_management.test_manager
Procedure
Navigate to All > Test Management 2.0 > Test Execution Suites.
In the form, fill in the fields:
Field Description Name Unique name for the test execution suite. Planned start date Planned date and time for starting the test execution suite. Planned end date Planned date and time for ending the test execution suite. Planned duration Estimated duration for the test execution suite. This duration is the difference between the planned start date and the planned end date. Number Automatically generated number for the test execution suite. State Current state of the test execution suite. Assignment group Group working on test execution suite. Field Description Percent complete Percentage of test execution suites that have been completed. Value is calculated automatically. Percent passed Percentage of test execution suites that have passed. Value is calculated automatically. Percent failed Percentage of test execution suites that have failed. Value is calculated automatically. Percent blocked Percentage of test execution suites that were blocked. Value is calculated automatically. Click Submit.
What to do next
- To add tests to the test execution suite, click Add tests. From the Tests list, select the required tests, and click Add to Execution Suite.
- To add test sets to the test execution suite, click Add test sets. From the Test Sets list, select the required test sets, and click Add to Execution Suite.
- In the Test execution assignments related list, select the test and assign it to a user.
Parent Topic:Testing using Test Management 2.0