Capacity in Strategic Planning

The Capacity tab provides portfolio managers a comprehensive view of capacity, allocations, and utilization of resources.

Analyzing the Capacity screen, you can:

  • View resource capacity for prioritized items in your portfolio.
  • Understand the resource capacity needs and estimates across your organization by using key attributes such as group, role, and skill.
  • Effectively forecast the supply of resources and the demand of work in your portfolio.
  • Understand and get an overview of the resource capacity allocations by using the color indicators.
  • Plan for resources with specific skills or roles for future assignments.
  • View the resource allocation health instantly with the new intuitive user interface that gives you a detailed breakdown of portfolio duration by month having over allocations.
  • Identify the risks in resource capacity for the prioritized planning items using the Rank field.
  • Use the warning icons to easily identify the over utilized resources (
Image omitted: cp-over-utilized-icon.png
Over utilized resource icon.\), planning items with actual dates \(\[Omitted image "cp-wip-gantt-bar-icon.png"\] Alt text: In-progress icon for planning items with actual dates.\), and the planning items or resource groups with no resource assignments \(\[Omitted image "cp-no-rsrc-asgnmnts-icon.png"\] Alt text: No resource assignments icon.\).
Image omitted: cp-capacity-planning-screen.png
Capacity screen.

The top screen area displays:

  • Resource capacity details depending on the defined resource criteria.
  • Allocation details for the time period.
  • Resources grouped by primary attributes.

The bottom screen area displays:

  • Prioritized planning items.
  • Interactive Gantt chart for the duration of planning items. Select a Gantt bar to see the capacity for that specific planning item only.

    Note: Move the Gantt bar of a planning item to adjust the planned dates depending on the available resource capacity. Planning items with actual dates, indicated with in-progress icon (

Image omitted: cp-wip-gantt-bar-icon.png
In-progress icon for planning items with actual dates.\), cannot be adjusted for resource availability.
  • Toggle option (
Image omitted: cp-toggle-buttons.png
Toggle options to view capacity.\) to adjust the resource capacity view.
  • Legend explaining the visual representation of the resource capacity and Gantt bar of planning items.
Image omitted: cp-legend.png
Legend chart for Capacity screen.

Parent Topic:Exploring Portfolio Planning in Strategic Planning Workspace