Use Resource Finder to analyze resource availability
Search and analyze resource availability using the Resource Finder, so that you can create resource plans for a project or demand.
Before you begin
Role required: it_project_manager, it_demand_manager, or resource_manager
About this task
In the Resource Finder, search for the resources that you need, and create a plan for the selected resources.
- Steps 1 and 2 take you to the resource finder.
- Step 3 provides guidance on different options to filter and analyze the resources availability. Choose the options that suit your needs.
- Step 4 shows how to create resource plan for the selected resources.
Procedure
- Open the Resource Plans page for a project or demand.
| Option | Steps |
|---|---|
| From a project |
|
| From a demand |
|
Select the project or demand in the resource grid section and click the resource finder icon .
The resource finder section opens at the bottom of the page. A list of up to 50 records are displayed initially. If you have more than 50 resources, you can load them by clicking Get More.
Use the following options to filter and analyze the capacity of the resources.
| Option | Description |
|---|---|
| Display available or over allocated resources | Using the Show/Hide menu to filter resources by available or over allocated. |
| Perform a simple search | Search the resources by group, role, or user attributes, by selecting the search criteria. |
| Build your own search criteria | Use the advanced search to add your filter conditions. For example, select Search by group, click Advanced, then click the Advanced search filter icon . Here you can add conditions to filter this group further. Note: While adding filters, ensure that you do not add an AND condition for different values of the same attribute. For example, do not filter the user group with conditions for Skill X AND Skill Y. |
| View the availability of the resources for an extended duration | Use the options from the date range selector. From the Australia release onwards, you can select a custom date range. The value of the property Maximum time duration in Resource Finder in months determines the maximum duration for which the resource details are displayed in the resource finder. |
| Analyze the resources list | Use the Configuration menu to analyze different constraints such as the capacity, availability, actual hours, and others for different time periods. By default, only the Availability hours are displayed. To view other details, select Detailed View , and select the required columns from the Configuration menu . Displaying the requested hours for a user group or role helps you understand immediately if you need to fulfill any resource requests and to do so, if you have enough capacity for that user group or role. The Requested column would not be available in the Configuration menu under the following conditions.
All non-project events created for a user from the calender appear as Operational Work for the user in Resource Finder. |
| Update the capacity of a resource | Right-click on the user and select Update Capacity. |
- Select the resources you want to create resource plans for and select Add New Plan.
Result
- The resource plan is created in the Planning state with zero planned hours.
The resource plan appears as a row at the top in the resource plan list of the project or demand. Based on the type of resource selected in finder, the resource plan has one of the following prefixes:
- [G] for a resource plan created for a group.
- [R] for a role resource plan created for a role.
- [U] for a user resource plan created for a user. Note: The resource plan that is created last appears at the top in the resource plan list of a project or demand.
What to do next
- Update the planned hours for the resource plan using the resource grid.
- To view and update more details for the resource plan, click the information icon in the beginning of the resource plan row.
- You can now request the resource plan.
Parent Topic:Resource plans
Related topics
Create an operational resource plan
Confirm and allocate a resource plan
Request a change to a resource plan
Recalculate costs of a resource plan
Update cost plan related to a resource plan
Complete an allocated resource plan
Request extension of an allocated resource plan
Allocate resources for the extended period