Update task dependency details in Project Workspace

Update the details of the dependency including its type and lag time from Project Workspace.

Before you begin

Role required: it_project_manager

Procedure

  1. Open a project from the home page of Project Workspace.

    For information, see Access the Project Workspace.

  2. Open the dependency side panel in one of the two ways.

    OptionAction
    From the data gridFrom the dependency column, select the dependency of the task.
    From the timeline viewSelect the dependency line.
  3. Edit the fields.

  4. Select Update.

Parent Topic:Add internal project task dependencies from Project Workspace