Skip to content
Release: Australia · Updated: 2026-03-12 · Official documentation · View source

Create tasks from project task creator

Use the project task creator to create multiple tasks at once.

Before you begin

Role required: it_project_manager

Procedure

  1. In the Project form, right-click the header bar and select Project task creator.

  2. Enter the number of tasks to create.

  3. Select the Create FS dependency check box to create a finish-to-start dependency between these tasks (when the first task finishes, the next task starts).

    Clear the check box to create the tasks with no dependencies.

  4. Select OK.

    The new tasks appear in the Project Tasks related list. The application automatically creates a task Number and a Short Description that starts with Auto Created Task, followed by a number when more than one task is created.

Parent Topic:Create a project task from a project