Enable cost rollup calculations
Enable rollup calculations from the project properties.
Before you begin
Role required: it_project_manager
Procedure
Navigate to All > Project > Settings > Preferences.
Select Enable project cost rollup.
Select Save.
Result
Rollup values are read-only on forms. Point to the icon beside the field for a tooltip message.
Image omitted: Rollup\_popup.png
Tooltip message
Tooltip message
Parent Topic:Create a project cost plan