Create baseline of a project

Create a schedule baseline and financial baseline of a project. A schedule baseline captures planned dates of all tasks and milestones at a particular moment in time. A financial baseline captures benefit and financial metric information (snapshot of cost plan, benefit plan, and project-level financial metrics) at a particular moment in time.

Before you begin

Role required: it_project_manager

About this task

Schedule baseline

You can create as many schedule baselines as necessary and review the changes that have been made to the project since the previous baseline. If a project is not on schedule, you can create a schedule baseline to know how much schedule slippage has occurred. It also helps to view the real-time deviations between actual and planned values.

The baseline appears as a set of gray lines below the bars that represent the actual tasks on the Gantt chart. These baselines represent planned dates, while the task bars represent the actual dates. If the project tasks are shifted to the right of the baselines, the project is running behind schedule.

Financial baseline

You can create as many financial baselines as necessary and compare them to review the financial changes that have been made to the project since the previous baseline. Any financial baseline does not capture actual cost component of the project.

Note: Nested projects cannot have baselines. Baselines are allowed for the top-level projects only.

Procedure

  1. Navigate to All > Project > Projects > All.

  2. Select the required project.

  3. To create schedule and financial baselines of a project, use any of the following options.

OptionSteps
From the Financials tab
  1. Open a project from planning page in Project Workspace.
  2. Select the Financials and select Create baseline.
  3. In the Create Baseline pop-up, enter a suitable name and description.
  4. Select Save.
From the Project Workspace
  1. Open a project from planning page in Project Workspace.
  2. Select the baseline icon (
    Image omitted: icon-baselines.png
    Baseline icon.).</li>
  3. In the Create Baseline pop-up, enter a suitable name and description.
  4. Select Save.
From a related link
  1. Select the Create Baseline related link.
  2. In the Create Baseline pop-up, enter a suitable description.
  3. Select Save.
From a related list
  1. Select the Baselines related list.
  2. Select the Create Baseline button.
  3. In the Create Baseline pop-up, enter a suitable name and description.
  4. Select Save.
**Note:** In the Create Baseline pop-up, the **Create Schedule Baseline** and the **Create Financial Baseline** check boxes are selected by default. Clear a check box if you do not intend to create a specific baseline.
  • Compare financial baselines of a project
    Compare baselines to review the variances in the financial data of a project and see what changed.
  • Compare schedule baselines of a project
    Compare baselines to review variance between tasks and identify which task has variance from the current planned end date and the baseline end date. The baseline variance column displays the amount of variance between the two date comparisons.

Parent Topic:Starting a project

Related topics

Create a project task from a project

Create a parent-child relationship on the Project Task form

Create a monetary benefit plan for a project

Create a non-monetary benefit plan for a project

Associate monetary and non-monetary benefit plans

Create a project cost plan

Recalculating costs of all resource plans in a project

Create an expense line

Create and manage waterfall projects

Update a project

Copy a project

Assign a project schedule

Create a milestone

Activate project task email notifications

Change the planned start date of a project

Create a cost type definition

Costing add-on in Project Management

Generate labor costs

Create a project status report

Allocate budget to a project

Migrate budget of active projects to Next Experience

Migrate financial baselines of projects to Next Experience

Compare financial baselines of a project

Compare schedule baselines of a project