Planned Task Relationship form

Learn about the fields of planned task relationship form.

FieldDescription
PredecessorThe predecessor, or determiner, in the relationship. You can select a new task. However, it is a good practice to delete the relationship and create a new relationship between the correct tasks.
SuccessorThe successor in the relationship. The successor depends on the predecessor. You can select a new task. However, it is a good practice to delete the relationship and create a new relationship between the correct tasks.
TypeThe type of relationship, which is always Predecessor of::Successor of. Do not change this value.
Sub TypeThe type of dependency.
LagThe lag time between the tasks. The Enter the days, hours, minutes, and seconds for the lag. Lag time can be positive or negative.