Compare financial baselines of a project
Compare baselines to review the variances in the financial data of a project and see what changed.
Before you begin
Role required: it_project_manager
About this task
You can create multiple baselines at various stages of a project, for example, at the end of each phase or after every calendar month or quarter. Each baseline captures the financial data of the project at a particular moment, providing a basis from which you can identify and review the changes made to the project. Having multiple baselines and comparing them helps you track the performance of your projects.
Procedure
- To compare the financial baselines of a project, use one of the following options.
| Option | Steps |
|---|---|
| From the Project Workspace |
|
| From the Project form |
|
| From the Baseline form |
|
On the Financial Baseline form, select the baselines you want to compare from the two choice lists.
By default, the current and the most recent baselines are selected.
Select Compare.
The comparative data of the baselines display in the following two sections:
- The Financial Baseline Summary section displays four widgets: the first two widgets contain the financial data of the two baselines, the third widget contains their variance, and the fourth widget contains the actual costs to date of the project.
The Financial Baseline Details section displays the cost plans and benefit plans of the two baselines in two different grids. Each plan type has two rows corresponding to each baseline data.
Note: Select the baseline legend icon (
Baseline Legend info icon.\) to see the color code of rows representing each baseline.
Review additional fields or reorganize the comparative data on the form.
- To show or hide additional fields on the widgets in the Financial Baseline Summary section, select the configuration icon (
Configuration icon\) and select the field names.
The selected field preferences are saved and are available when you reopen the Financial Baseline form. To reset to the default widget layout, select **Reset to defaults**.
- To view cost plan or benefit plan comparative data in yearly, quarterly, or monthly format, select the **Year** or **Quarter** or **Month** views respectively.
- To toggle viewing the **Financial Baseline Summary** section, select the **Collapse** icon \(
Collapse icon\) or **Expand** icon \(\[Omitted image "ExpandIcon.png"\] Alt text: Expand icon\).
Parent Topic:Create baseline of a project