Create a work order task for an Enterprise Asset Management work order
Create a work order task to track and manage an individual task for your Enterprise Asset Management work order.
Before you begin
Role required: wm_agent
Procedure
Navigate to Workspaces > Enterprise Asset Workspace > Work management.
On the Work orders tab, select the work order to which you want to add a work order task.
The work order record opens.
Select the Work Order Tasks tab and select New.
On the Create New Work Order Task form, fill in the fields.
| Field | Description |
|---|---|
| Work Order Task | |
| Assignment group | Agent group to which the work order task is assigned. |
| Assigned to | Agent to whom the work order task is assigned. |
| Work type | Type of work that the assigned agent must perform on the associated enterprise asset. The options are Break Fix, Install, Planned Maintenance, Asset condition, Shutdown, Startup,and Calibration. |
| Asset | Enterprise asset that the assigned agent is performing work on. This field populates automatically. |
| Location | Current location of the associated enterprise asset. This field populates automatically.Note: If you select a linear asset, the Work order linear asset location icon Image omitted: pencil-outline-24.svg appears to enable you to choose the work order location between the Start marker and End marker. To select a location, follow these steps:</p>
A Map location form appears, showing the start and the end markers on the map.
|
| Start marker | Start point of the linear asset or the linear asset.Note: This field only appears if you select Linear asset or linear segment from the Asset field. |
| End marker | End point of the linear asset or the linear segment.Note: This field only appears if you select linear asset or linear segment from the Asset field. |
| Short description | Brief description of the work order task. |
| Description | Detailed description of the work order task. |
| Work notes | Notes about the work order task that are visible to all users within your organization. |
| Scheduling | |
| Window start | Estimated start date and time of the work order task. |
| Window end | Estimated completion date and time of the work order task. |
| Estimated work duration | Amount of time that you estimate it will take to complete the work order task. |
| Actual work start | Actual start date and time of the work order task. |
| Actual work end | Actual completion date and time of the work order task. |
- Select Save.
Result
- The work order task is created in the Draft state.
- Assets associated with the work order are added to the work order task and listed on the Affected assets tab.