Reassign assessor for a risk assessment project
Reassign assessors for multiple in-progress risk assessment projects simultaneously to minimize disruptions during stakeholder transitions.
Before you begin
Role required: sn_risk_advanced.risk_asmt_project_manager
Procedure
Navigate to All > Risk > Risk Workspace.
Select the list
Image omitted: list-icon-riskworkspace.png
List icon. icon.
List icon. icon.
From the list, navigate to Risk assessment projects, and select In progress.
Select the Risk Assessment projects for which you want to reassign assessors.
Reassign project dialog box appears.
In the Reassign project dialog box, select the assessor in the Select assessor field.
Select Confirm.
Parent Topic:Risk assessment project