Reschedule the planned work order
Reschedule planned work orders by advancing or delaying the occurrence date of the schedule.
Before you begin
Role required: sn_fsm_planned_wm.planned_work_admin
About this task
Avoid generating duplicate work orders for overlapping schedule occurrences by changing the start or end date, either advancing or delaying the maintenance work as needed.
Note: You can modify a schedule occurrence only if either no work orders are generated for it or the work orders generated for it are in the Draft state.
Procedure
Navigate to All > Field Service Management > Planned Work Management > Plans.
Open your work plan.
In the Planned Work Schedules related list, select a schedule for which you want to review the schedule occurrences.
In the Schedule Occurrences related list, select a schedule occurrence that you want to modify.
Update the Earliest start date or Requested due by field to change the date and time of the existing schedule occurrence.
Select Update.